From CANNA JULY 2010 |
We have posted some new photos on the Web Album. You can click here or go to the following address: http://picasaweb.google.es/VilaVerdeSantaMaria
We have also had the revised completion dates since the strike action has terminated.
They are as follows:
· C1: Lantana - Completion for 30.09.2010
· C2: Cactus - Completion for 08.11.2010
· C12: Raphis - Completion for 29.11.2010
· C13: Malaleuca - Completion for 10.12.2010
· Villas: Completion for 25.11.2010
· Townhouses: Completion from Septemeber 2010 to November 2010
If you have any questions please contact us on info@tecnicil.com
Thanks for the update on completions dates. However, what does C2, C12, C13 etc mean? Which communities are these? Yours confused...
ReplyDeleteCan we have some updated photos on Cactus please
ReplyDeleteAny chance of pics of Raphis/Cactus ?
ReplyDeleteI assume this C1, C2, C12, C13 relates to Canna
ReplyDeleteAny news on Raphis?
Apologies for the confusion with the unit codes. CANNA is C04 and has been complete for more than a year. The codes here relate only to buildings that are yet to finish.
ReplyDeleteWe have filled in the names of the communities for you.
Updated pics of cactus would be appreciated
ReplyDeleteWhat is the dates for properties still awaiting confirmation that ok for second snag e.g Ficus
ReplyDeleteAnonymous said...
ReplyDeleteUpdated pics of 4 bed villas would be appreciated
Second snags are ongoing on all completed properties with reported defects etc. Please coordinate directly with your representatives on Sal and our team there.
ReplyDeleteany pics of Cactus
ReplyDeleteOur townhouse is on Yucca - what is the latest on this. We don't seem to get any informationon Yucca.
ReplyDeletepictures of cactus please..............
ReplyDeleteany pics of raphis and cactis
ReplyDeleteWe have posted photos a few days ago for you.
ReplyDelete