Sunday, November 15, 2009

Almost there!


Although Sunday, I think it important to let you all know that we have had the news we've all been waiting for: ELECTRA have signed the paperwork so now the electricity issue has been resolved!

Here is the communication we have received from our main Engineer

Autos assinados pela Electra quer dizer que, a partir daquela data (da assinatura) esta reconhece que a rede está em condições de uso para o serviço, tomou posse da mesma, passando a ser da sua exclusiva responsabilidade o fornecimento de electricidade a cada uma das unidades concluídas.

So what this mean, in English is:

The order has been signed by Electra which means that, from that date (The signing date) they (Electra) recognise that the network is fit for use, they take possession of it thus exclusive responsibility for the supply of electricity to each of the finished units passes to them.

So it really does appear that the "light" at the end of the tunnel can be switched on!

Friday, November 13, 2009

Updated photos on the Vila Verde Webalbum

Once again we have updated the photos. We have tried to make the most comprehensive photo report possible. If you want photos of other parts of the resort just let us know and we'll send our team (Well, Carlos anyway) out with his camera.

Have a great day!


http://picasaweb.google.com/VilaVerdeSantaMaria/November2009?feat=directlink

Wednesday, November 11, 2009

Vila Verde is becoming "Verde"

The first plants have been put into the grounds around Canna. In total there is something like two million Euros worth of plants that have been ordered for Vila Verde.

Now we will see our fantastic resort not only taking shape but gaining colour!



These first plants have gone into Canna (C04) and I am sure you will agree that they really give the resort an attractive finish. We will plant Canna and then move on to Sedum (C07) and so on, more or less in the order of the communities that have finished up to now.
We are sure you are as excited and proud as we are to see this and we would like to thank everyone on site for a great job.
We will post all of the photos on the Picasa Web Album that we have.




































Tuesday, November 10, 2009

Furniture Update

We have been placing furniture in finished apartments, not necessarily always in apartments that have gone to deeds, and in many cases we have not proceeded to install the furniture as some owners have indicated they wish to have the snagging inspections finalised first.

However, just to keep you all updated. I have some figures on furniture in the first three communities.

In SEDUM (C07) Community we have now placed 28 packages. The installation of air conditioning in these units should be next.

In Aloe (C05) we have 9 packages (Bear in mind that there are only 28 apartments in Aloe)

In Canna (C04) we have 24 deliveries made.

If you have bought furniture and you are on one of these communities and would like to know if the furniture is in, please drop us a line on info@tecnicil.com

We will be placing more furniture as the days go by.

Have a great evening.

Saturday, October 31, 2009

Electra and Tecnicil

Over the past few months you are surely aware that we have had our ups and downs when it comes to the power and water. Mainly downs, if we are to be honest.

The attitude we had was that it was best not to burden you with the constant and sometimes quite strange battles we had to try and get our resort connected to the national utility company.

However given the positive feedback we have had even with the sharing of not so positive informaiton I thought we would tell you where we are at the moment. Or at least, where We believe we are.

Electra did a follow up and final inspection on the resort. Here is in the communication we had:

Recepção Provisória ELECTRICIDADE pela Electra:
Em 21 Out.09 fez-se a vistoria final de Electricidade com a Electra.

No dia 23, o Engº Miranda (responsável Electra no Sal) enviou informação para a Electra (S. Vicente), sobre a vistoria, não havendo nada de relevante que obste à assinatura do Auto (informação colhida na vistoria).Os autos foram assinados pelos Empreiteiros, Fiscalização e Dono da Obra e enviados para Electra (S. Vicente).

This says that on the 23rd Engineer Miranda, the man responsible for electricity on Sal Island sent information to his HQ on the island of Sau Vicente that shows there is no relevant obstacle to the signing of the order [for connection]. The orders were signed by the contractors, the onsite management company and the owner of the works (That's us, at Tecnicil Imobiliaria) and sent to Electra in Sau Vicente.

Once Electra have signed this "Auto" then the electricity can be signed up.

The water situation is one step behind this. The communication we have internally is this:


Foi solicitado à Electra, há cerca de 2 semanas, vistoria da rede de águas (solicitado para dia 13 Out.).

O técnico responsável sobre quem recai a acção é o Engº Neves (Electra) que já recebeu orientações do Planeamento da Electra para proceder á vistoria.

Contudo, até ao presente ainda não conseguiu marcar data

Nearly two weeks ago I requested of Electra that they sign off on the water network (requested for October 13th).

The technician in charge of this, Engineer Neves (Electra) has already received instructions from Electra's Planning Department to carry out the inspection.

However, up to know he has not managed to give us a date.

So you can see that in theory we are right on the cusp of having electricity and a hair's breadth from the water. I say "In theory" because there could still be some delay on Electra's side. However there should be no other obstacles to having power and water.

As soon as we have more communication we will put it here for you all.

Friday, October 30, 2009

Dates for your diary

We have finally had some dates back from the different construction divisions on Sal Island. These are dates to which we have added a margin of safety so it is very likely that the units are finished earlier. However, we have accepted that we need to improve our communication and in the spirit of this have decided to post all of our dates. We will update them as we go along and will answer any many questions as possible.

Please bear in mind that there is no one "reason" for the delays. The Cape Verde Islands present a logistic challenge to us and indeed any other company and we are working as hard as we can.


Apartments
Phase One

C07 - SEDUM - COMPLETED
C04 - CANNA - COMPLETED
C05 - ALOE - COMPLETED
C11- COPROSMA -COMPLETED
C03 - ATRIPLEX - COMPLETED / Snagging Ongoing
C09 - PEPPER - COMPLETED / Snagging Ongoing
C08 – FICUS - February 28th
C06 - CALLISTEMON - January 30th
C10 - TASSEL - December 30th


Phase Two
C01- LANTANA - April 30th
C02 - CACTUS -May 30th
C12 - RAPHIS - May 30th
C13 - MELALEUCA - June 30th


Villas

A78/A89 - January 30th
A29/A40 - February 30th
A41/A51 - March 30th
A68/A77 - April 30th
A52/A67 - May 30th
A1/A28 - May 30th


Townhouses

B3-33 /37 – YUCCA - February 28th
B3-29 /32 - YUCCA - March 30th
B3-21 /28 -YUCCA - March 30th
B3-12 /20 - YUCCA - April 30th
B3-7 /11 - WASHINGTONIA - April 30th
B3-1 /6 - WASHINGTONIA -April 30th
B2-30 /34 - WASHINGTONIA -April 30th
B2-24 /29 - WASHINGTONIA - May 30th


As the building and completing goes on we will have more workers focused on a gradually reducing number of units so we do hope that these dates will not be accurate. But we do guarantee that they will kept updated if we do see any changes.
Once again, all comments welcome and if you have any questions about your particular unit or situation please write to us on info@tecnicil.com
Have a great weekend!